Activity Duration

Venkataramiah S Annapragada
23/12/2018 0 0

Number of work periods needed to complete the activity.
Duration of an activity is calculated using the Task Rule which is as follows :

             Work = Duration * Resource Units

i.Work is the Effort estimated for the activity. Various Estimation techniques discussed previously can be used. This is usually expressed in hours.

ii.Resource Units equals the number of resources that are assigned to the activity and the number of hours per day they are available for this activity.

iii.Duration calculated from above Rule is usually expressed in days.

Example :

An High Level Design Document is required to be prepared. It’s estimated effort is 40 hours. Two resources are assigned to it. Both of them can spare 4 hours each daily for this activity. What is the Duration of this Activity ?

0 Dislike
Follow 1

Please Enter a comment

Submit

Other Lessons for You

Effective grasping of any lesson
Our mind is extremely volatile with thoughts. When it comes to learning a new skill or new set of knowledge concentration plays a key role. Try this before a class: Close your eyes, take few deep breaths...

What is M.S.Project ?
MICROSOFT PROJECT contains project work and project groups, schedules and finances.Microsoft Project permits its users to line realistic goals for project groups and customers by making schedules, distributing...

Points to be remembered while creating Project schedule in MS Project
Rule 1 : First task should not have predecessors, Last task should not have successors. Rule 2 : Except first and last tasks, every task must have both predecessors and successors. Rule 3 : Project Summary...

7 Simple Ways to Make Your Day More Productive
There are only so many hours in a day. Being more productive means getting more out of the limited time we have available. Despite how productive you might already be, odds are you can enhance your productivity...

Points to be remembered while creating Project schedule in MS Project
Rule 1 : First task should not have predecessors, Last task should not have successors. Rule 2 : Except first and last tasks, every task must have both predecessors and successors. Rule 3 : Project Summary...
X

Looking for PMP Training Classes?

The best tutors for PMP Training Classes are on UrbanPro

  • Select the best Tutor
  • Book & Attend a Free Demo
  • Pay and start Learning

Learn PMP Training with the Best Tutors

The best Tutors for PMP Training Classes are on UrbanPro

This website uses cookies

We use cookies to improve user experience. Choose what cookies you allow us to use. You can read more about our Cookie Policy in our Privacy Policy

Accept All
Decline All

UrbanPro.com is India's largest network of most trusted tutors and institutes. Over 55 lakh students rely on UrbanPro.com, to fulfill their learning requirements across 1,000+ categories. Using UrbanPro.com, parents, and students can compare multiple Tutors and Institutes and choose the one that best suits their requirements. More than 7.5 lakh verified Tutors and Institutes are helping millions of students every day and growing their tutoring business on UrbanPro.com. Whether you are looking for a tutor to learn mathematics, a German language trainer to brush up your German language skills or an institute to upgrade your IT skills, we have got the best selection of Tutors and Training Institutes for you. Read more