Lesson Posted on 24/12/2018 Learn MS Project +1 PMP Training

Earned Value Analysis

Venkat Annapragada

I have been corporate trainer for 8 years. I have conducted sessions in India as well as abroad. The...

It Compares Performance Measurement Baseline to the actual schedule and cost performance. Performance Measurement Baseline integrates Scope Baseline, Schedule Baseline and Cost Baseline. For each work package the following dimensions are calculated : Planned Value . Work that was planned to have... read more

It Compares Performance Measurement Baseline to the actual schedule and cost performance. Performance Measurement Baseline integrates Scope Baseline, Schedule Baseline and Cost Baseline.

 

For each work package the following dimensions are calculated :

  • Planned Value [PV]. Work that was planned to have been completed at a given point of time
  • Budget At Completion [BAC]. Total planned value for the project. Also called Cost Baseline
  • Earned Value [EV]. The measure of work performed at a given point of time
  • Actual Cost [AC]. The total cost incurred to complete the work measured in EV

 Percentage Project Complete at a given point of time. Percentage of EV/BAC

read less
Comments
Dislike Bookmark

Lesson Posted on 24/12/2018 Learn MS Project +4 PMP Training Business Analysis Training IIBA CBAP Training CAPM Training

Project Management Business Documents

Venkat Annapragada

I have been corporate trainer for 8 years. I have conducted sessions in India as well as abroad. The...

Project Business Case It documents the economic feasibility of the project. It is prepared before starting the project and can result in a go/no-go decision for the project. One of the criteria for determining project success. The input for Business Case is needs assessment. Project Benefits Management... read more

Project Business Case

It documents the economic feasibility of the project. It is prepared before starting the project and can result in a go/no-go decision for the project. One of the criteria for determining project success. The input for Business Case is needs assessment.

Project Benefits Management Plan

It documents how and when the benefits of the project will be delivered — one of the criteria for determining project success. The inputs for Benefits Management Plan are needs assessment and Project Business Case.

Project Charter

Issued by Project Sponsor and formally authorises the project’s existence. The input for Project Charter is Business Case

read less
Comments
Dislike Bookmark

Lesson Posted on 24/12/2018 Learn MS Project +1 PMP Training

Work Performance Reports

Venkat Annapragada

I have been corporate trainer for 8 years. I have conducted sessions in India as well as abroad. The...

These are the collection of Work Performance Information. These are distributed to aid decision making and increase awareness of project status. The reports are circulated to all relevant project stakeholders in communications processes. These reports may contain one or more of following : Status... read more

These are the collection of Work Performance Information. These are distributed to aid decision making and increase awareness of project status. The reports are circulated to all relevant project stakeholders in communications processes.

These reports may contain one or more of following :

  • Status updates
  • Earned value graphs,
  • Trends and forecasts
  • Burndown charts
  •  Risk Summaries
read less
Comments
Dislike Bookmark

Learn MS Project from the Best Tutors

  • Affordable fees
  • Flexible Timings
  • Choose between 1-1 and Group class
  • Verified Tutors

Lesson Posted on 24/12/2018 Learn MS Project +1 PMP Training

Agreements

Venkat Annapragada

I have been corporate trainer for 8 years. I have conducted sessions in India as well as abroad. The...

A contract is a mutually binding agreement. It obligates the seller to provide the deliverables and the buyer to make the payment on delivery. It is a legal document recognised in the court of law The agreement includes the following : Procurement statement of work Schedule of deliveries Pricing... read more

A contract is a mutually binding agreement. It obligates the seller to provide the deliverables and the buyer to make the payment on delivery. It is a legal document recognised in the court of law

 

The agreement includes the following : 

  • Procurement statement of work
  • Schedule of deliveries
  • Pricing and Payment Terms
  • Acceptance criteria
  • Incentives and penalties
  • Warranty support
  • Standard contract clauses – Force Majeure, Liquidated Damages, Change handling, Termination
  • Claims Administration and Alternative Dispute Resolution
read less
Comments
Dislike Bookmark

Lesson Posted on 24/12/2018 Learn MS Project +3 PMP Training Project Management CAPM Training

Critical Path Method

Venkat Annapragada

I have been corporate trainer for 8 years. I have conducted sessions in India as well as abroad. The...

This method involves the following steps : Calculate the Duration for all activities on the Task Network Diagram. Calculate the early start , early finish , late start and Late Finish for all activities by using Forward pass and Backward pass techniques. Identify the number of paths on the Network... read more

 This method involves the following steps :

  • Calculate the Duration for all activities on the Task Network Diagram.
  • Calculate the early start [ES], early finish [EF], late start [LS] and Late Finish [LF] for all activities by using Forward pass and Backward pass techniques.
  • Identify the number of paths on the Network Diagram.
  • Calculate the total duration of each path.
  • Identify the path with the longest duration. This path is called Critical Path.
  • The Critical Path Duration will be the MINIMUM Project Duration.
  • Calculate Total Float for all activities with the formula [LS-ES] or [LF-EF].
  • Total Float is the amount of time an activity can be delayed without delaying the project finish date. The float is also called as Slack.
  • Identify Activities on Critical Path. These will have zero float which means they HAVE to start and finish on time.
read less
Comments
Dislike Bookmark

Lesson Posted on 23/12/2018 Learn MS Project +3 PMP Training Project Management CAPM Training

Activity Duration

Venkat Annapragada

I have been corporate trainer for 8 years. I have conducted sessions in India as well as abroad. The...

Number of work periods needed to complete the activity.Duration of an activity is calculated using the Task Rule which is as follows : Work = Duration * Resource Units i.Work is the Effort estimated for the activity. Various Estimation techniques discussed previously can be used. This... read more

Number of work periods needed to complete the activity.
Duration of an activity is calculated using the Task Rule which is as follows :

             Work = Duration * Resource Units

i.Work is the Effort estimated for the activity. Various Estimation techniques discussed previously can be used. This is usually expressed in hours.

ii.Resource Units equals the number of resources that are assigned to the activity and the number of hours per day they are available for this activity.

iii.Duration calculated from above Rule is usually expressed in days.

Example :

An High Level Design Document is required to be prepared. It’s estimated effort is 40 hours. Two resources are assigned to it. Both of them can spare 4 hours each daily for this activity. What is the Duration of this Activity ?

read less
Comments
Dislike Bookmark

Learn MS Project from the Best Tutors

  • Affordable fees
  • Flexible Timings
  • Choose between 1-1 and Group class
  • Verified Tutors

Lesson Posted on 01/02/2017 Learn MS Project +1 MSP

What is Baseline and what is the use of baseline in MSP (Microsoft Project)

Vikas Chauhan

I am a freelance and providing Excel / MIS training and MIS Job Work. Having 9+yrs of experience as...

What is baseline - The baseline in MSP (Microsoft project) management refers to the first version of the schduled project (after approval on draft version) timelines (duration), cost, resource and scope. Basline usaually store - Project Start and End Date Timelines (duration) of project Planned... read more

What is baseline - The baseline in MSP (Microsoft project) management refers to the first version of the schduled project (after approval on draft version) timelines (duration), cost, resource and scope. Basline usaually store -

  • Project Start and End Date
  • Timelines (duration) of project
  • Planned and Buddgested Cost

What is the use of baseline - Basline helps to track / monitore project with current project with timelines, duration, cost and resource. The baseline is nothing but a forzen picture of project (snapshot of project).

Set a baseline (Copied from Microsft website)

  1. On the View tab, in the Task Views group, click Gantt Chart.

    Task View Area image.

  2. If you are setting a baseline for specific tasks, select the tasks, including subtasks and summary tasks, that you want to include in your baseline plan. (If you are setting a baseline for the entire project, skip this step.)

    TIP: To select adjacent tasks, hold down SHIFT, and then click the first and last tasks that you want. To select nonadjacent tasks, hold down CTRL, and then click each task that you want. You can select up to 10 tasks at one time.

  3. Click the Project tab. In the Schedule group, point to Set Baseline, and then click Set Baseline.

    create baseline graphic

  4. Click Set baseline, and then select the baseline that you want to set.

  5. Under For, do one of the following:

    • To set the baseline for all data in the project, click Entire Project.

    • To set the baseline for only the tasks that you selected in the Gantt Chart view, click Selected tasks.

  6. Under Roll up baselines, select how you want baseline data to be rolled up:

    • To all summary tasks     Select this check box if you want updated baseline data for the selected tasks to be rolled up to the corresponding summary tasks. Otherwise, baseline data for summary tasks may not accurately reflect subtask baseline data.

    • From subtasks into selected summary task(s)     Select this check box if you want baseline data for selected summary tasks to be updated to reflect both deletions of subtasks and added tasks for which you previously saved baseline values.

      NOTE: If you selected both subtasks and their summary tasks, select both check boxes.

Set an interim plan

  1. Click the Project tab. In the Schedule group, point to Set Baseline, and then click Set Baseline.

    create baseline graphic

  2. Click Set interim plan.

  3. In the Copy box, click the start and finish or baseline values that you want to save. (The current start and finish, and baseline values are not numbered.)

  4. In the Into box, click the name of the interim plan into which you want to copy the values.
    Interim plans are stored in the start and finish fields.

    NOTE: If you select one baseline in the Copy box and another baseline in the Into box, you will save a baseline, rather than an interim plan. All baseline data will be copied. If you select a baseline in the Copy box, and a start and finish interim plan in the Into box, only the start date and finish date from the baseline will be copied to the interim plan.

  5. Click Entire project or Selected tasks to save the portion of the schedule that you want.

read less
Comments
Dislike Bookmark

Lesson Posted on 30/12/2016 Learn MS Project +1 Project Management

MS Project: Delete Calendar

Mahtia Business Solutions Pvt. Ltd.

"24x7 Coach" provides education on Project Management, Technology and Soft skills training for working...

In MS Project, you may want create custom calendar and later you may want to delete if it is not necessary. This video explains how to delete a calendar in MS Project 2016 Professional.
Comments
Dislike Bookmark

Lesson Posted on 30/12/2016 Learn MS Project +1 Project Management

MS Project: Linking tasks of other projects

Mahtia Business Solutions Pvt. Ltd.

"24x7 Coach" provides education on Project Management, Technology and Soft skills training for working...

In MS Project, user may want to create a dependancy between tasks of multiple projects, which is also called as external dependancy. This video explains how to create external dependancy in MS Project 2016 Professional and explains usage of 'Links between Projects' command in Project Tab in MS Project... read more

In MS Project, user may want to create a dependancy between tasks of multiple projects, which is also called as external dependancy. This video explains how to create external dependancy in MS Project 2016 Professional and explains usage of 'Links between Projects' command in Project Tab in MS Project 2016 Professional.

read less
Comments
Dislike Bookmark

Learn MS Project from the Best Tutors

  • Affordable fees
  • Flexible Timings
  • Choose between 1-1 and Group class
  • Verified Tutors

Answered on 05/03/2015 Learn MS Project

Adarsh P.

Drop me message.. I have learn concepts of NS3. May be I can help you out.
Answers 8 Comments
Dislike Bookmark

About UrbanPro

UrbanPro.com helps you to connect with the best MS Project Training in India. Post Your Requirement today and get connected.

Overview

Lessons 16

Total Shares  

+ Follow 9,462 Followers

Top Contributors

Connect with Expert Tutors & Institutes for MS Project

x

Ask a Question

Please enter your Question

Please select a Tag

X

Looking for MS Project Classes?

The best tutors for MS Project Classes are on UrbanPro

  • Select the best Tutor
  • Book & Attend a Free Demo
  • Pay and start Learning

Learn MS Project with the Best Tutors

The best Tutors for MS Project Classes are on UrbanPro

This website uses cookies

We use cookies to improve user experience. Choose what cookies you allow us to use. You can read more about our Cookie Policy in our Privacy Policy

Accept All
Decline All

UrbanPro.com is India's largest network of most trusted tutors and institutes. Over 55 lakh students rely on UrbanPro.com, to fulfill their learning requirements across 1,000+ categories. Using UrbanPro.com, parents, and students can compare multiple Tutors and Institutes and choose the one that best suits their requirements. More than 7.5 lakh verified Tutors and Institutes are helping millions of students every day and growing their tutoring business on UrbanPro.com. Whether you are looking for a tutor to learn mathematics, a German language trainer to brush up your German language skills or an institute to upgrade your IT skills, we have got the best selection of Tutors and Training Institutes for you. Read more